Report for February 2014

Report Date
February 2014

Achievements this period

  • A further two development iterations have been successfully completed. Details of the delivered functionality can be seen on the iteration pages at Iteration 2.0A and  Iteration 2.0B
  • Release 2.1 went live on 3rd March.
  • Procurement Office are continuing with the live data set-up
  • The project has now entered the maintenance phase, where the developers work only on minor enhancements and user feedback in preparation for formally handing over a stable application to support.

Issues

  • Further unavailability of Test Polopoly (3 days) has interfered with development and testing

Next steps

  • Complete maintenance iteration and release the final version
  • Project closure

 

 

Target dateTitle
14-Mar-2014End of Maintenance
28-Mar-2014Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
184.0 days
Activity this month
44.6 days
Activity this year
167.0 days
Activity to date
167.0 days
Estimate to complete current year
19.2 days
Estimate to complete future years
0.0 days

Project Info

Project
Supplier and contract database (Buy@Ed)
Code
PPS006
Programme
Z. Procurement (PPS)
Management Office
ISG PMO
Project Manager
Dawn Holmes
Project Sponsor
Karen Bowman
Current Stage
Close
Status
Closed
Start Date
22-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Mar-2014
Programme Priority
2
Overall Priority
Normal