Report for March

Report Date
March 2014

Achievements this period

  • The maintenance iteration was successfully completed this month with a variety of minor enhancements and bug fixes being developed.
  • The 3rd and final realease of Buy@Ed was promoted to Live - Release 2.2 notes
  • Handover of technical and support documents took place
  • A closure meeting was held to sign-off the completion report and formally close the project

Issues

  • Further outage of Test Polopoly which affected development & testing. This was escalated to WIS.

Next steps

  • Close the project

 

 

Target dateTitle
28-Mar-2014Closure

 

Project Status
RAG Status
Overall
BLUE
Change Status
Activity
Approved budget
184.0 days
Activity this month
19.0 days
Activity this year
186.2 days
Activity to date
186.2 days
Estimate to complete current year
0.2 days
Estimate to complete future years
0.0 days

Project Info

Project
Supplier and contract database (Buy@Ed)
Code
PPS006
Programme
Z. Procurement (PPS)
Management Office
ISG PMO
Project Manager
Dawn Holmes
Project Sponsor
Karen Bowman
Current Stage
Close
Status
Closed
Start Date
22-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Mar-2014
Programme Priority
2
Overall Priority
Normal