Report for December 2017
- Report Date
- December 2017
Achievements to date
-
Project brief - meeting held to review and updates agreed
-
Project Plan created / dates to be realigned taken into consideration activity under RES069
-
v5.7 JIRAs being investigated and escalated with Elsevier
-
Agreement to hold joint update meetings with RES069 and Support team as projects are closely aligned and similar resource assigned
Issues
- Outstanding JIRAs reviewed with Elsevier contact as current response is to fix in next release this is noted as v5.10 and not v5.7 this raised a number of risks to the support of the application until the fix is available
- Project Manager request is being progressed expecting contract PM CVs in next couple of weeks to cover shortlisting and interviews
Next Steps
-
Project brief final sign off and approval
-
Continue with upgrade 5.7 into test environment
-
Complete UAT for v5.7
-
Preparation for Live upgrade currently scheduled for end of January
-
Communication to users groups to be issued
The project status is AMBER due to project brief sign off delayed and key issues raised to supplier
- Approved budget
- 50.0 days
- Activity this month
- 1.8 days
- Activity this year
- 2.3 days
- Activity to date
- 2.3 days
- Estimate to complete current year
- 46.0 days
- Estimate to complete future years
- 0.0 days