Report for January 2018
- Report Date
- January 2018
Achievements to date
-
Project brief -approval completed
-
Upgrade of Test environment to v5.7
-
User Acceptance Testing completed for v5.7 and acceptance signed off
-
Preparation for Live upgrade completed - Service Alert, GoCAB
-
Communication to users groups issued
-
Upgrade to v5.7 Live environment completed
-
Upgrade of Dev environment to v5.9 underway
-
New PM resourced
Issues
- Fixes identified in 5.7 wont be fixed until 5.10 release
- Decision with consultation from supplier to move straight from 5.7 to 5.9 - revised milestones and any surplus resource days (24 days) change requested back to programme
Next Steps
-
Handover to new PM starting on 5th February
-
Confirm Dev environment completed on upgrade to v5.9
-
Implement Web Services work
-
Upgrade Test Environment to v5.9
-
UAT for v5.9
The project status is GREEN
- Approved budget
- 46.0 days
- Activity this month
- 5.4 days
- Activity this year
- 7.6 days
- Activity to date
- 7.6 days
- Estimate to complete current year
- 39.3 days
- Estimate to complete future years
- 0.0 days