Report for November 2017

Report Date
November 2017

Achievements this period:

  • Agreed resource required to deliver the project
  • Completed Sprint 1 of the project deliverable
  • Software review complete
  • JIRA updated and tasks designed
  • Started sprint 2 that covers documenting the code, creating a test harness, Unit Testing the BAGIT libraries and upgrade BAGIT to V5.
  • HLD agreed.  

Issues

  • Performance, issues seen during testing need to be reviewed once BAGIT is upgraded to V5.
  • Current Bagit library has many snags that need resolving, may need to look for a more established library.
  • There are now 41 software issues that need resolving before deployment of the 'must haves' code.
  • SSL bug between archive and worker means that the users credentials can not be verified.  

Risks - Full Service Solution:

  • Need to write up the LLD for the project.  

Next Steps

  • Continue with SCRUM of the project  
  • Resource

  • SPEED David JAVA engineer harness document code
  • PETIT William JAVA engineer CI 
  • HAMILTON George JAVA core build 
  • D'MELLOW Kenton Encryption
  • KNOWLES Claire TA
  • MARCH Jon SCRUM master
  • Note re budgets:   This project has a mix of capital and revenue budgets, and core funding on this project.  The revenue budget is a fixed cost for RSS effort and the other teams are core funded, so there is not effort tracking against budget on this project.
  •  
  • Mielstones

  •  
  • 16-Nov-2017
  • 15-Dec-2017
  • 19-Jan-2018
  • 23-Feb-2018
  • 12-Mar-2018
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
125.0 days
Activity this month
24.0 days
Activity this year
33.0 days
Activity to date
33.0 days
Estimate to complete current year
36.0 days
Estimate to complete future years
92.0 days

Project Info

Project
Data Vault
Code
RSS022
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Lawrence Stevenson
Project Sponsor
Robin Rice
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
08-Feb-2017
Planning Date
16-Oct-2018
Delivery Date
25-Jan-2019
Close Date
15-Mar-2019
Overall Priority
Highest
Category
Discretionary