Report for December 2017
- Report Date
- December 2017
Achievements in Last Period
- Sprints 1-4 completed - significant BagIT (deposit) build, test and remediation completed
- Sprint 5 in progress - UI wire framing, resolution BagIt filenaming issues, review deposit encryption. TSM API selection
- Draft resource plan created for review with EDINA resourcing manager
- Joint project meeting held with University of Manchester team
Issues
- Availability of EDINA and other resources to meet project delivery dates (demonstration and minimal viable product (MVP))
- Delay in selection of cloud storage hosting service (e.g. Oracle, gCloud)
- Integration of user UUN with Pure/data vault to identify deposit owners
- Key management processes need definition and implementation
Next Steps
- Review resource plan with EDINA and revise schedule in line with agreements
- Start Sprint 6 - UI branding, resolve UUN issue, start deposit encryption tests, Pure metadata retrieval, identify cloud service
- Build full test server
Milestones
Target Date |
Title |
Stage |
Complete |
|
16-Oct-2017 |
Scrum approach adopted; first sprint started; project tasks added to Jira |
Planning | Yes |
|
26-Jan-2018 |
Full test server operational |
Build | No |
|
16-Feb-2018 |
Demonstration of deposit archiving and retrieval to internal (TSM) and external cloud storage | Demonstration | No |
|
11-May-2018 |
Minimal viable product (MVP) for Data Vault available for use | MVP | No |
|
25-May-2018 |
Project closure |
Closure | No |
- Approved budget
- 125.0 days
- Activity this month
- 24.0 days
- Activity this year
- 33.0 days
- Activity to date
- 33.0 days
- Estimate to complete current year
- 36.0 days
- Estimate to complete future years
- 92.0 days