Report for May 2018

Report Date
May 2018
Achievements in Last Period
  • UI/Broker integration completed

  • Pure flat file interface developed

  • Cloud archive supplier (Oracle) selected using G-Cloud 9 framework

  • UAT planning in progress

  • GDPR PIA in progress

  • Production and performance testing environments designed and sized; VMs requested

  • ITI HashiCorp Vault service to be used for key management

  • Schools UAT teams identified

Risks/Issues
  • Oracle cloud contract needs to be in place before soft launch
  • Completion of GPR PIA may be a risk to soft launch
Next Steps
  • Complete production and performance testing environment builds
  • Run UAT to start week 11/06/2018
  • Run full end-to-end performance tests
  • Run Schools workshops for potential DV users in June
  • Prepare G-Cloud 9 framework call-off contract for Oracle cloud service
  • Complete GDPR privacy impact assessment (PIA)
  • Prepare Service Level Definition (SLD)
  • Deliver DV soft launch on 26/06/2018

Milestones

Target Date
Title
Stage
Complete
11-Oct-2017 Full service solution initial planning complete Plan Yes

16-Oct-2017

Scrum approach adopted; first sprint started; project tasks added to Jira

Plan Yes
02-Feb-2018 Website wireframes approved Design Yes
28-Feb-2018 Deposit/retrieval/encryption (TSM) completed Build Yes
06-Mar-2018 Website UI screens completed Build Yes
30-Mar-2018 GDPR review  in progress Analyse Yes
13-Apr-2018 Deposit/retrieval/encryption (Cloud) completed Build Yes
20-Apr-2018 Full test server operational Build Yes
23-Apr-2018 Demonstration of deposit archiving and retrieval to internal (TSM) and  external cloud storage Deliver Yes
25-May-2018 Integration testing completed Integrate Yes
25-May-2018 Minimal viable product (MVP) for Data Vault available (interim UI) Deliver Yes
07-Jun-2018 Test user training completed Deliver No
08-Jun-2018 Production environment available Deliver No
21-Jun-2018 UAT completed Accept No
22-Jun-2018 Data Vault GDPR compliant Deliver No
22-Jun-2018 Cloud service contract in place Deliver No
26-Jun-2018 Data Vault soft launch Deliver No
27-Jul-2018 Project closure approved Close No
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Risks/Issues - Cloud service contract needs to be in place and GDPR PIA completed by soft launch
Change Status
Activity
Approved budget
468.0 days
Activity this month
58.0 days
Activity this year
320.0 days
Activity to date
320.0 days
Estimate to complete current year
101.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Data Vault
Code
RSS022
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Lawrence Stevenson
Project Sponsor
Robin Rice
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
08-Feb-2017
Planning Date
16-Oct-2018
Delivery Date
25-Jan-2019
Close Date
15-Mar-2019
Overall Priority
Highest
Category
Discretionary