Report for June 2018

Report Date
June 2018
Achievements in Last Period
  • G-Cloud 9 framework call-off contract completed and sent to Oracle

  • Test environment build in progress but behind schedule

  • HashiCorp Vault service for key management in place; links to be configured

  • GDPR PIA in progress

Risks/Issues
  • Cloud contract also requires completion of Oracle paperwork; still not received; UAT at risk
  • HashiCorp key management integration still to be configured
Next Steps
  • Integrate Oracle archive service into test and live environments
  • Complete HashiCorp Vault key management integration
  • Complete test and live environment builds
  • Run UAT to start week 09/07/2018
  • Run full end-to-end performance test
  • Run Schools workshops for potential DV users in July 
  • Complete GDPR privacy impact assessment (PIA)
  • Prepare Service Level Definition (SLD)
  • Deliver DV soft launch on 23/07/2018

Milestones

Target Date
Title
Stage
Complete
11-Oct-2017 Full service solution initial planning complete Plan Yes

16-Oct-2017

Scrum approach adopted; first sprint started; project tasks added to Jira

Plan Yes
02-Feb-2018 Website wireframes approved Design Yes
28-Feb-2018 Deposit/retrieval/encryption (TSM) completed Build Yes
06-Mar-2018 Website UI screens completed Build Yes
30-Mar-2018 GDPR review  in progress Analyse Yes
13-Apr-2018 Deposit/retrieval/encryption (Cloud) completed Build Yes
20-Apr-2018 Full test server operational Build Yes
23-Apr-2018 Demonstration of deposit archiving and retrieval to internal (TSM) and  external cloud storage Deliver Yes
25-May-2018 Integration testing completed Integrate Yes
25-May-2018 Minimal viable product (MVP) for Data Vault available (interim UI) Deliver Yes
06-Jul-2018 Cloud service contract in place Integrate No
06-Jul-2018 HashiCorp key management in place for test environment Integrate No
06-Jul-2018 Full test environment in place Integrate No
09-Jul-2018 UAT start Accept No
13-Jul-2018 Production environment available Deliver No
20-Jul-2018 UAT completed Accept No
20-Jul-2018 Data Vault GDPR compliant Deliver No
23-Jul-2018 Data Vault soft launch Deliver No
17-Aug-2018 Project closure approved Close No
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Issue - Oracle cloud service and HashiCorp key management will not be in place for UAT scheduled for 09/07/2018
Change Status
Activity
Approved budget
468.0 days
Activity this month
48.5 days
Activity this year
368.5 days
Activity to date
368.5 days
Estimate to complete current year
45.0 days
Estimate to complete future years
30.0 days

Project Info

Project
Data Vault
Code
RSS022
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Lawrence Stevenson
Project Sponsor
Robin Rice
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
08-Feb-2017
Planning Date
16-Oct-2018
Delivery Date
25-Jan-2019
Close Date
15-Mar-2019
Overall Priority
Highest
Category
Discretionary