S/w defect found during Interim Service testing fixed and proven.
Storage design completed sufficiently well to allow equipment quote and lead time query to be completed.
Risk around kit not being procured in tome for end of budget period resolved.
Issues
Interim service go-live date of end of April missed due to time required to address s/w issue found during testing. New live date TBC.
Next Steps
Complete interim solution re-testing.
Order equipment.
Complete planning
Milestones:
No current milestones - all activities in planning.
Note re budgets: This project has a mix of capital and revenue budgets, and core funding on this project. The revenue budget is a fixed cost for RSS effort and the other teams are core funded, so there is not effort tracking against budget on this project.