Report for April 2017

Report Date
April 2017
  • Achievements this period:
    • S/w defect found during Interim Service testing fixed and proven.
    • Storage design completed sufficiently well to allow equipment quote and lead time query to be completed.
    • Risk around kit not being procured in tome for end of budget period resolved.
  • Issues
    • Interim service go-live date of end of April missed due to time required to address s/w issue found during testing.    New live date TBC.  
  • Next Steps
    • Complete interim solution re-testing.
    • Order equipment.
    • Complete planning
  • Milestones:
    • No current milestones - all activities in planning.
  • Note re budgets:   This project has a mix of capital and revenue budgets, and core funding on this project.  The revenue budget is a fixed cost for RSS effort and the other teams are core funded, so there is not effort tracking against budget on this project.
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Interim solution has been delayed (issue). This should not have a significant impact on the main solution go-live, however, a firm target date for this has not been identified yet, and there is a risk, which has not yet been fully explored , that the new infrastructure will not be purchased in time to meet the end of the current financial year \ budget period.
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Data Vault
Code
RSS022
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Lawrence Stevenson
Project Sponsor
Robin Rice
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
08-Feb-2017
Planning Date
16-Oct-2018
Delivery Date
25-Jan-2019
Close Date
15-Mar-2019
Overall Priority
Highest
Category
Discretionary