Report for September 2018
- Report Date
- September 2018
Achievements in Last Period
-
Production environment available for performance testing
-
First phase of UAT completed
-
Project re-planned in line with delays caused by performance issues
-
Performance tuning in progress
-
SLD document ready for approval
Risks/Issues
- DataStore performance issues
- Early adoption period removed from current project scope
Next Steps
- Run second phase of UAT
- Apply performance tuning and rerun tests
- CAHSS workshop scheduled for 30/10/2018
- Arrange workshops for MVM and SciEng
- Finalise GDPR DPIA with stakeholders
- Approve Service Level Definition (SLD)
- Soft launch rescheduled to 12/11/2018
Milestones
Target Date |
Title |
Stage |
Complete |
| 11-Oct-2017 | Full service solution initial planning complete | Plan | Yes |
|
16-Oct-2017 |
Scrum approach adopted; first sprint started; project tasks added to Jira |
Plan | Yes |
| 02-Feb-2018 | Website wireframes approved | Design | Yes |
| 28-Feb-2018 | Deposit/retrieval/encryption (TSM) completed | Build | Yes |
| 06-Mar-2018 | Website UI screens completed | Build | Yes |
| 30-Mar-2018 | GDPR review in progress | Analyse | Yes |
| 13-Apr-2018 | Deposit/retrieval/encryption (Cloud) completed | Build | Yes |
| 20-Apr-2018 | Full test server operational | Build | Yes |
| 23-Apr-2018 | Demonstration of deposit archiving and retrieval to internal (TSM) and external cloud storage | Deliver | Yes |
| 25-May-2018 | Integration testing completed | Integrate | Yes |
| 25-May-2018 | Minimal viable product (MVP) for Data Vault available (interim UI) | Deliver | Yes |
| 31-Jul-2018 | Cloud service contract in place | Integrate | Yes |
| 03-Aug-2018 | Key management system in place for test environment | Integrate | Yes |
| 03-Aug-2018 | Full test environment in place | Integrate | Yes |
| 08-Sep-2018 | Production environment available for performance testing | Integrate | Yes |
| 15-Sep-2018 | UAT phase 1 completed | Accept | Yes |
| 26-Oct-2018 | UAT phase 2 completed | Accept | No |
| 26-Oct-2018 | Performance testing/tuning completed | Accept | No |
| 05-Nov-2018 | Data Vault GDPR compliant | Deliver | No |
| 12-Nov-2018 | Data Vault soft launch/early adoption period | Deliver | No |
| 07-Dec-2018 | Project closure approved | Close | No |
- Approved budget
- 468.0 days
- Activity this month
- 27.5 days
- Activity this year
- 65.0 days
- Activity to date
- 385.5 days
- Estimate to complete current year
- 103.5 days
- Estimate to complete future years
- 0.0 days