Report for June 2017

Report Date
June 2017
  • Achievements this period:

    • Agreement reached on the approach re data protection and encryption for the Interim Service.

    • Coding contractor has joined the team.
    • All designs approved (does not include encryption).
    • Interim Service lined up to go-live on 12th July.
    • Equipment orders placed for one of the two DCs  
  • Next Steps
    • Equipment orders placed for the second DC (carried over from last period).
    • Cloud provision option identified and agreed order placed (carried over from last period).  
  • Risks - Full Service Solution:
    • The project has been asked to ensure that the solution can accommodate non-research data.   Non-research data is more tightly controlled than research data from a data protection perspective, and it is currently unknown what the impact will be on the time line from accommodating this.

    • .We do not yet have an agreed approach for dealing with personal or other sensitive data or the use of encryption on the Full Service Solution.
    • Our new coding contractor is not making the initial progress that was expected. We do not yet know what impact this will have on our overall time line.
    • A full decision on a cloud service provider has not yet been reached. Oracle is the preferred supplier within the project team but a formal selection process needs to be gone through.  We are progressing with coding work on the assumption that Oracle will be selected.   It is currently assumed this delay will not affect our overall time line.
    • There have been further delays with the purchase of storage infrastructure equipment within the Backup Infrastructure Upgrade project.   We do not yet now what the impact will be on out time line yet.
    • The policy for the Interim Service is that no personal data should be stored on the system.  We are relying on depositors adhering to this policy, but there is a Risk that personal data may make it on to the system.

Milestones

Date

RAG

Interim service solution planning complete

22 Mar          

Complete.

Interim service solution go-live 

12th Jul

G

Full service solution technical designs and BOMs complete

16th Jun

Complete

Full solution initial planning complete.

16th Jun

G

Full service DC infrastructure installed and ready to use

14 Aug

A

Full solution Technical Builds and app complete and tested

31 Oct

A

Service Go Live (not including data migration from the Interim Service)      .

02 Nov

A

Deployment sign off

16 Nov

A

 

Note re budgets:   This project has a mix of capital and revenue budgets, and core funding on this project.  The revenue budget is a fixed cost for RSS effort and the other teams are core funded, so there is not effort tracking against budget on this project.

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Project has returned to green following re-planning with new go-live target dates (based on a number of assumptions).
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Data Vault
Code
RSS022
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Lawrence Stevenson
Project Sponsor
Robin Rice
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
08-Feb-2017
Planning Date
16-Oct-2018
Delivery Date
25-Jan-2019
Close Date
15-Mar-2019
Overall Priority
Highest
Category
Discretionary