Report for Septmeber 2017
- Report Date
- September 2017
- Achievements this period:
- Requirements document complete, reviewed and issued.
- List of software components added to Jira and grouped.
- Top level delivery project plan created.
- Identification of additional features captured.
- Issues
- Current Bagit library has many snags that need resolving, may need to look for a more established library.
- There are 37 software issues that need resolving before deployment of the 'must haves' code.
- SSL bug between archive and worker means that the users credentials can not be verified.
- Risks - Full Service Solution:
-
Need to write up the HLD and the LLD for the project.
-
We need the EDINA resource available to the project to continue the coding tasks.
-
The current software build needs to be reviewed for quality an unknown bugs.
-
Limitations in library files may determine maximum data length.
- Next Steps
- Update the project brief with new requirements and review with Tony Wier.
- Review current code of software build.
- Review status of DataVault against COTs and doing nothing and provide a set of risks and bebefits for each.
-
Note re budgets: This project has a mix of capital and revenue budgets, and core funding on this project. The revenue budget is a fixed cost for RSS effort and the other teams are core funded, so there is not effort tracking against budget on this project.
- Approved budget
- 0.0 days
- Activity this month
- 9.0 days
- Activity this year
- 9.0 days
- Activity to date
- 9.0 days
- Estimate to complete current year
- 16.0 days
- Estimate to complete future years
- 0.0 days