Report for October 2017
- Report Date
- October 2017
- Achievements this period:
- Agreed resource required to deliver the project
- Completed Sprint 1 of the project deliverable
- Software review complete
- JIRA updated and tasks designed
- Started sprint 2 that covers documenting the code, creating a test harness, Unit Testing the BAGIT libraries and upgrade BAGIT to V5.
- HLD agreed.
- Issues
- Performance, issues seen during testing need to be reviewed once BAGIT is upgraded to V5.
- Current Bagit library has many snags that need resolving, may need to look for a more established library.
- There are now 41 software issues that need resolving before deployment of the 'must haves' code.
- SSL bug between archive and worker means that the users credentials can not be verified.
- Risks - Full Service Solution:
-
Need to write up the LLD for the project.
-
-
Next Steps
- Continue with SCRUM of the project
- Resource
- SPEED David JAVA engineer harness document code
- PETIT William JAVA engineer CI
- HAMILTON George JAVA core build
- D'MELLOW Kenton Encryption
- KNOWLES Claire TA
- MARCH Jon SCRUM master
Note re budgets: This project has a mix of capital and revenue budgets, and core funding on this project. The revenue budget is a fixed cost for RSS effort and the other teams are core funded, so there is not effort tracking against budget on this project.
- Approved budget
- 125.0 days
- Activity this month
- 24.0 days
- Activity this year
- 33.0 days
- Activity to date
- 33.0 days
- Estimate to complete current year
- 36.0 days
- Estimate to complete future years
- 92.0 days