- Report Date
- July 2017
Achievements this period
- Further update to the trial documentation and LTW evaluation of the success criteria have been made following input and feedback.
- Programme Owner agree to assist with securing sign-off and project closure
Issues
- No business sign-off on documentation and evaluation report
Next steps
- Obtain sign off on all documents including closure report
- Approved budget
- 10.0 days
- Activity this month
- 0.3 days
- Activity this year
- 8.8 days
- Activity to date
- 8.8 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days