Report for August 2017

Report Date
August 2017

Achievements this period

Issues

  • None

Next steps

  • None
Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Activity
Approved budget
10.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
10.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
ExamOnline Trial
Code
SCE011
Programme
SCE Portfolio Projects (OTHSCE)
Management Office
ISG PMO
Project Manager
Muriel Mewissen
Project Sponsor
David Cavanagh
Current Stage
Close
Status
Closed
Start Date
20-Oct-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
28-Aug-2017
Programme Priority
1
Overall Priority
Normal
Category
Discretionary