- Report Date
- June 2017
Achievements this period
- Trial documentation and LTW evaluation of the success criteria have been updated following input and feedback.
- Closure report circulated for sign-off.
Issues
- No business sign-off on documentation and evaluation report
Next steps
- Obtain sign off on all documents including closure report
- Approved budget
- 10.0 days
- Activity this month
- 0.5 days
- Activity this year
- 8.6 days
- Activity to date
- 8.6 days
- Estimate to complete current year
- 1.4 days
- Estimate to complete future years
- 0.0 days
This article was published on