- Report Date
- June 2018
Achievements
- Metrics for business case identified and documented in Project Approach Report
- Marketing activities identified and documented in Project Approach Report
- Metric and marketing activities implemented as set out in Project Approach Report
- Project Sponsor sign off given to suspend project
- WIS approved project suspension
Issues
Next Steps
- Project will restart on 1st October 2018
- Approved budget
- 10.0 days
- Activity this month
- 2.0 days
- Activity this year
- 4.8 days
- Activity to date
- 4.8 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 4.3 days