Report for December 2019
- Report Date
- December 2019
Report for December 2019 by Ken Miller
Achievements
- Hosting work to be progressed for Live.
- Url addressing for each instance agreed so that hosting completed.
Issues
Next Steps
- Project closure
Milestones
Present milestones will need to be revised:
| Stage | Milestone | Due Date | Complete |
|---|---|---|---|
| Plan |
End of Planning |
09-Nov-2018 | Yes |
| Analyse | Analysis Completed | 30-Nov-2018 | Yes |
| Deliver | Sprint 1 Completed | 15-Feb-2019 | Yes |
| Deliver | Sprint 2 Completed | 22-March-2019 | Yes |
| Deliver | Sprint 3 Completed | 26-April-2019 | Yes |
| Deliver | Sprint 4 Completed | 31-May-2019 | Yes |
| Deliver | Sprint 5 Completed | 30-Aug-2019 | Yes |
| Deliver | Delivery Completed | 20-Sept-2019 | Yes |
| Close | Project Closure | 04-Oct-2019 | No |
- Approved budget
- 70.0 days
- Activity this month
- 1.1 days
- Activity this year
- 18.0 days
- Activity to date
- 68.6 days
- Estimate to complete current year
- 1.6 days
- Estimate to complete future years
- 0.0 days