Report for January 2020
- Report Date
- January 2020
Report for January 2020 by Ken Miller
Achievements
- Project closure drafted. Delay required to allow Production Management's input regarding support agreement.
- Raise support arrangements with Production Management.
- CSCE project closure meeting.
Issues
Next Steps
- Production Management support agreement and closure approval.
- Project closure
Milestones
Present milestones will need to be revised:
| Stage | Milestone | Due Date | Complete |
|---|---|---|---|
| Plan |
End of Planning |
09-Nov-2018 | Yes |
| Analyse | Analysis Completed | 30-Nov-2018 | Yes |
| Deliver | Sprint 1 Completed | 15-Feb-2019 | Yes |
| Deliver | Sprint 2 Completed | 22-March-2019 | Yes |
| Deliver | Sprint 3 Completed | 26-April-2019 | Yes |
| Deliver | Sprint 4 Completed | 31-May-2019 | Yes |
| Deliver | Sprint 5 Completed | 30-Aug-2019 | Yes |
| Deliver | Delivery Completed | 20-Sept-2019 | Yes |
| Close | Project Closure | 04-Oct-2019 | No |
- Approved budget
- 70.0 days
- Activity this month
- 1.8 days
- Activity this year
- 19.9 days
- Activity to date
- 70.5 days
- Estimate to complete current year
- 0.8 days
- Estimate to complete future years
- 0.0 days