August 2016
- Report Date
- August 2016
Achievements in Last Period
- Liaison with colleagues at Ulster have continued.
Issues
- Ongoing resource issue at Ulster - escalated to senior management there and awaiting response at time of writing.
- It was thought that they might respond at the last TOPdesk conference but this didn’t happen.
Next Steps
- The project has requested 3 days of unplanned contingency to upgrade Ulster when it is possible.
- As soon as Ulster is positioned to engage with us they will be upgraded.
Milestones
|
Date |
Milestone |
|
15-Jun-2016 |
Delivery Sign Off (Edinburgh) |
|
21-Jun-2016 |
Install to Production Instances Stirling, Ulster & Sheffield |
|
27-Jul-2016 |
Final Delivery Sign Off Review |
|
29-Jul-2016 |
Project Close |
- Approved budget
- 3.0 days
- Activity this month
- 1.0 day
- Activity this year
- 1.0 day
- Activity to date
- 70.0 days
- Estimate to complete current year
- 4.0 days
- Estimate to complete future years
- 0.0 days