UniDesk Annual Upgrade - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
September 2018 BLUE 345.0 days 364.0 days 0.0
Content
Status
Closed
Current Stage
Close
Start Date
Thursday, 1 June 2017
Planning Date
Friday, 29 September 2017
Delivery Date
Tuesday, 5 June 2018
Close Date
Friday, 28 September 2018
Project information
Project Code
SMI018
Programme
ISG - IT Service Management (SMI)
Session
17/18
16/17
Organisational Unit
IS Applications
Project Management Office (if relevant)
ISG PMO
Project Category
Compliance
Funding Source
Core
Programme Priority
2
Overall Priority
Higher