Report for Aug 2016
- Report Date
- August 2016
Interim mid-month report ( as of 11-Aug 2016)
Achievements in Last Period
- Extended peer testing and user acceptance testing in progress
- Support JIRA has been deployed to LIVE
- Progress has been made on the remaining JIRAs. There are a few outstanding bug to be addressed.
Issues
- Bugs raised during peer testing need to be fixed before being handed over to the business for final round of UAT
- Deployment coincides with a busy time in August so deployment has to avoid Confimration and Clearing on 17 and 18-Aug. This was re-arranged to the 25/08/16.
- Support JIRA has been requested to be put live ahead of the others. This however took longer to fix and as a result, the original deployment date of 25/08/16 had to be delayed.
- Time has increased due to further development work required.
- Developer is scheduled to go on a training course which will potentially delay the revised deployment date.
Next Steps
- Complete bug fixes ahead of re-planned UAT Acceptance sign-off review
- Get Special CAB approval to deploy to LIVE after 12 Sept
- Complete dev work on the Database Migration , and schedule future dates for acceptance sign-off and deployment for the Data Migration
Milestones
| 16-Sep-2016 | WP1 User Acceptance Sign-off |
| 16-Sep-2016 | WP2 User Acceptance Sign Off |
| 21-Sep-2016 | WP2 Deploy to LIVE |
| 21-Sep-2016 | WP1 Deploy to LIVE |
| 03-Oct-2016 | Database Migration - Deploy to LIVE |
| 05-Oct-2016 | WP1 Deployment sign off review |
| 05-Oct-2016 | WP2 Deployment Sign Off Review |
| 14-Oct-2016 | Database Migration User Acceptance |
| 31-Oct-2016 | Project Closure |
- Approved budget
- 142.0 days
- Activity this month
- 16.0 days
- Activity this year
- 16.0 days
- Activity to date
- 152.0 days
- Estimate to complete current year
- 13.0 days
- Estimate to complete future years
- 0.0 days