January 2016

Report Date
January 2016

Achievements in Last Period

  • Complete planning with two work packages rather than one single work package.
  • Specify requirements for Bamboo implementation and implement Bamboo for UG & PG Admin and Databases.

 

Issues

  • None

 

Next steps

  • Schedule regular team meetings.
  • Start build on Work Package One

 

01-Apr-2016WP1 Deploy to TEST
02-May-2016WP1 User Acceptance Sign-off
09-May-2016WP1 Deploy to LIVE
23-May-2016WP1 Deployment sign off review
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
88.0 days
Activity this month
2.0 days
Activity this year
5.0 days
Activity to date
5.0 days
Estimate to complete current year
80.5 days
Estimate to complete future years
0.0 days

Project Info

Project
CAM - Enhancements to UG and PG Degree Finders
Code
STU251
Programme
Student Services (STU)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Niall Bradley
Current Stage
Close
Status
Closed
Start Date
04-Dec-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
08-Jun-2017
Programme Priority
1
Overall Priority
Normal
Category
Discretionary