Report for Jan 2018
- Report Date
- January 2019
Achievements this period
The revised design and proof on concept (POC) using the alternative products has been built.
Dev Services have been engaged to produce frontend re-design and build.
SEP has been consulted on taking the demonstrator to the next level. The timing for this is July 2019 when sufficient resources become available
Issues
- None
Next steps
- Build demonstrator application for hosting in test environment
Milestones
Target Date | Previous Date | Title | Stage | Complete |
---|---|---|---|---|
31-Aug-2017 | 30-Jun-2017 | End of Planning | Plan | Yes |
05-Feb-2018 | No date available | Unsuspend project and Kick off the development work | Execute | No |
11-May-2018 | 23-Mar-2018 | End of Planning (re-plan following suspension) | Plan | Yes |
25-May-2018 | No date available | System Design - Research PURE API | Design | Yes |
19-Jun-2018 | No date available | Build Complete | Build | Yes |
31-Oct-2018 | No date available | Deployment | Deliver | Yes |
25-Jan-2019 | No date available | Design | Design | No |
08-Feb-2019 | No date available | Build | Build | No |
28-Feb-2019 | No date available | Project Closure | Close | No |
External Milestones | ||||
21-Dec-2018 | 21-Dec-2017 | Guidance policy for use of "Willingness to take Ph.D. students" and "Ph.D. research projects available" | ||
21-Dec-2018 | 11-May-2017 | Guidance policy for use and tagging of keywords to support PGR search |
- Approved budget
- 100.0 days
- Activity this month
- 0.0 days
- Activity this year
- 9.9 days
- Activity to date
- 82.5 days
- Estimate to complete current year
- 10.0 days
- Estimate to complete future years
- 0.0 days