Report for Jan 2018

Report Date
January 2019

Achievements this period

The revised design and proof on concept (POC) using the alternative products has been built. 

Dev Services have been engaged to produce frontend re-design and build.

SEP has been consulted on taking the demonstrator to the next level.  The timing for this is July 2019 when sufficient resources become available

 

Issues

  • None

Next steps

  • Build demonstrator application for hosting in test environment

Milestones

Target Datesort descending Previous Date Title Stage Complete
31-Aug-2017  30-Jun-2017 End of Planning Plan Yes
05-Feb-2018 No date available       Unsuspend project and Kick off the development work Execute No
11-May-2018 23-Mar-2018 End of Planning (re-plan following suspension) Plan Yes
25-May-2018 No date available System Design - Research PURE API Design Yes
19-Jun-2018 No date available Build Complete Build Yes
31-Oct-2018 No date available Deployment Deliver Yes
25-Jan-2019 No date available Design Design No
08-Feb-2019 No date available Build Build No
28-Feb-2019 No date available Project Closure Close No
         
External Milestones        
21-Dec-2018 21-Dec-2017 Guidance policy for use of "Willingness to take Ph.D. students" and "Ph.D. research projects available"         
21-Dec-2018 11-May-2017 Guidance policy for use and tagging of keywords to support PGR search
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
100.0 days
Activity this month
0.0 days
Activity this year
9.9 days
Activity to date
82.5 days
Estimate to complete current year
10.0 days
Estimate to complete future years
0.0 days

Project Info

Project
PGR Opportunity Finder
Code
STU253
Programme
Student Services (STU)
Management Office
ISG PMO
Project Manager
Geoff Cropley
Project Sponsor
Jane Johnston
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
23-Jun-2016
Planning Date
11-May-2018
Delivery Date
08-Feb-2019
Close Date
28-Feb-2019
Programme Priority
3
Overall Priority
Normal
Category
Discretionary

Documentation