Report for February 2018
- Report Date
- February 2019
Achievements this period
Dev Services have been scheduled to handover the frontend design and build to LTW on March 8th 2019. This will be used in subsequent planning once SEP has taken the demonstrator on. The timing for this is estimated to be July 2019 when sufficient resources become available.
Issues
- None
Next steps
- Project closure
Milestones
| Target Date |
Previous Date | Title | Stage | Complete |
|---|---|---|---|---|
| 31-Aug-2017 | 30-Jun-2017 | End of Planning | Plan | Yes |
| 05-Feb-2018 | No date available | Unsuspend project and Kick off the development work | Execute | No |
| 11-May-2018 | 23-Mar-2018 | End of Planning (re-plan following suspension) | Plan | Yes |
| 25-May-2018 | No date available | System Design - Research PURE API | Design | Yes |
| 19-Jun-2018 | No date available | Build Complete | Build | Yes |
| 31-Oct-2018 | No date available | Deployment | Deliver | Yes |
| 25-Jan-2019 | No date available | Design | Design | No |
| 08-Feb-2019 | No date available | Build | Build | No |
| 28-Feb-2019 | No date available | Project Closure | Close | No |
| External Milestones | ||||
| 21-Dec-2018 | 21-Dec-2017 | Guidance policy for use of "Willingness to take Ph.D. students" and "Ph.D. research projects available" | ||
| 21-Dec-2018 | 11-May-2017 | Guidance policy for use and tagging of keywords to support PGR search |
- Approved budget
- 100.0 days
- Activity this month
- 0.0 days
- Activity this year
- 10.4 days
- Activity to date
- 84.0 days
- Estimate to complete current year
- 9.6 days
- Estimate to complete future years
- 0.0 days