Report for September 13

Report Date
September 2013

Achievements in Last Period

  • Iteration 1 completed
  • Iteration review meeting held 19/09/13
  • Goverance board members agreed
  • First board meeting scheduled

 

Issues

  •   A resource conflict for the senior developer's time has resulted in a three week pause of iterations. The second iteration will now commence in the 3rd week of October

 

Next Steps for October

  • Conditions of Satisfaction for stories progressing
  • Iteration planning meeting 11 October
  • Iteration 2 starts 15 October
  • Initial CAB progressing
  • Initial project board progressing
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
666.0 days
Activity this month
77.7 days
Activity this year
120.4 days
Activity to date
120.6 days
Estimate to complete current year
550.3 days
Estimate to complete future years
324.0 days

Project Info

Project
New University-wide Web CMS
Code
UWP006
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
31-Jul-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Jan-2016
Category
Discretionary