Report for November 2015

Report Date
November 2015

Achievements in Last Period

  • Healthcheck implemented on STAGING and LIVE

Issues

  • Due to availability, distribution documentation task moved out again until December
  • Roll back will now be deployed with UWP011

Next Steps

  • Complete Distribution Documentation
  • Complete Deployment Sign Off and Closure
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
1738.0 days
Activity this month
8.0 days
Activity this year
68.0 days
Activity to date
1749.0 days
Estimate to complete current year
2.0 days
Estimate to complete future years
0.0 days

Project Info

Project
New University-wide Web CMS
Code
UWP006
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
31-Jul-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Jan-2016
Category
Discretionary