Report for November 2015
- Report Date
- November 2015
Achievements in Last Period
- Healthcheck implemented on STAGING and LIVE
Issues
- Due to availability, distribution documentation task moved out again until December
- Roll back will now be deployed with UWP011
Next Steps
- Complete Distribution Documentation
- Complete Deployment Sign Off and Closure
- Approved budget
- 1738.0 days
- Activity this month
- 8.0 days
- Activity this year
- 68.0 days
- Activity to date
- 1749.0 days
- Estimate to complete current year
- 2.0 days
- Estimate to complete future years
- 0.0 days