Report for October 2013

Report Date
October 2013

Achievements in Last Period

  • Iteration 2 started and completed
  • First project board meeting held
  • Consultants for technical QA selected.
  • Core project team from Apps have moved into office together - enhancing comms

Issues

  •   Unix have not yet confirmed delivery for dates infrastructure

Next Steps for October

  • Iteration 3
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
666.0 days
Activity this month
66.9 days
Activity this year
190.0 days
Activity to date
191.0 days
Estimate to complete current year
486.0 days
Estimate to complete future years
324.0 days

Project Info

Project
New University-wide Web CMS
Code
UWP006
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
31-Jul-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Jan-2016
Category
Discretionary