February Report
- Report Date
- February 2016
Achievements in Last Period
- Release 5 now has 70 sites migrated to Live with 42 URL Switched to EdWeb
- Preparations for remaining 21 migrations due in March – 3 batches auto migration and 1 batch build in EdWeb due to their smaller size and limited number of pages
- Review of remaining project budget completed and possible return of days to UWP Programme
Issues
- A new risk has been raised around development work for Campus Maps under STU251 and any impact on UWP editorial tasks, a meeting has been scheduled for 3rd March to review.
- Issue encountered with Live migration for Careers similar to one experienced in Sept 2015 whereby connection pool stopped migration, resolved by restoring database and rerunning migration, when it was completed successfully.
Next steps
- Complete final automated migration to Live for Release 5
- Complete manual build of final sites
- 34 URL Switches to EdWeb Live for Vets / Careers / Health due in March
- 16 URL Switches to Edweb Live expected in April to complete project migration activity
The project current status is GREEN
19/04/16 Release 5 Migration Complete
29/04/16 Project closure
- Approved budget
- 347.0 days
- Activity this month
- 9.4 days
- Activity this year
- 86.3 days
- Activity to date
- 329.1 days
- Estimate to complete current year
- 20.4 days
- Estimate to complete future years
- 0.0 days