March Report

Report Date
March 2016

Achievements in Last Period

  • Release 5 now has 89 sites migrated to Live with 10 URL Switches to EdWeb remaining, 264 sites have been migrated as part of the overall project
  • All auto-migrations have now been completed, with all manual build of sites in EdWeb completed, with exception of Campus Maps
  • Campus maps - Development work is being completed by UWP team to create proxy and being testing, ready for handover to CAM team to complete editorial work

Issues

  • Issue encountered with Live migration for News similar to one previously experienced in Staging, this was resolved on second rerun of migration.

Next steps

  • Complete the final URLs Switches to EdWeb Live for News and CAM Themes on 12th and 19th April respectively
  • Complete migration script tidy up and documentation
  • Final VARNISH clean up
  • Complete project closure report for sign off
  • Close project

 

The project current status is GREEN

19/04/16    Release 5 Migration Complete

29/04/16    Project closure

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
347.0 days
Activity this month
10.5 days
Activity this year
99.5 days
Activity to date
341.3 days
Estimate to complete current year
8.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Content Migration to EdWeb
Code
UWP010
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Karen Stirling
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Start Date
25-Aug-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
06-May-2016
Programme Priority
2
Overall Priority
Higher
Category
Discretionary