April Report

Report Date
April 2016

Achievements in Last Period

  • Campus Maps - development completed, tested and deployed to Live ready for URL switching
  • All website migrations now completed - 265 sites
  • All Website URL switched to EdWeb including the University's Home Page on 19th April
  • Project Closure Questionnaire issued for completed and 11 responses recievd and included in project completion report
  • Project completion report updated and reviewed at a project closure review session to walkthrough project achievements and session learned
  • Testing completed for Apache and Final Polopoly redirects
  • Dev and Test migrate testing completed for Migration script clean up, ready to deploy to Staging and Live
  • Project team agreed that project can be signed off and closed

Issues

  • N/A

Next steps

  • Redirects Varnish / Apache to complete on 12th May
  • Migration scipt deploy to Live week commencing 16th May
  • Resource costs for these activities will be completed under UWP011 as per agreement with Tim Gray, Project Manager

 

 

Project Status
RAG Status
Overall
BLUE
Change Status
Activity
Approved budget
347.0 days
Activity this month
8.1 days
Activity this year
107.5 days
Activity to date
350.4 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Content Migration to EdWeb
Code
UWP010
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Karen Stirling
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Start Date
25-Aug-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
06-May-2016
Programme Priority
2
Overall Priority
Higher
Category
Discretionary