April Report
- Report Date
- April 2016
Achievements in Last Period
- Campus Maps - development completed, tested and deployed to Live ready for URL switching
- All website migrations now completed - 265 sites
- All Website URL switched to EdWeb including the University's Home Page on 19th April
- Project Closure Questionnaire issued for completed and 11 responses recievd and included in project completion report
- Project completion report updated and reviewed at a project closure review session to walkthrough project achievements and session learned
- Testing completed for Apache and Final Polopoly redirects
- Dev and Test migrate testing completed for Migration script clean up, ready to deploy to Staging and Live
- Project team agreed that project can be signed off and closed
Issues
- N/A
Next steps
- Redirects Varnish / Apache to complete on 12th May
- Migration scipt deploy to Live week commencing 16th May
- Resource costs for these activities will be completed under UWP011 as per agreement with Tim Gray, Project Manager
- Approved budget
- 347.0 days
- Activity this month
- 8.1 days
- Activity this year
- 107.5 days
- Activity to date
- 350.4 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days