Report for June 2017

Report Date
June 2017

Achievements in Last Period

  • Iteration 4 successfully completed
  • New functionality delivered for rendering scientific formulae using LaTeX.
  • A number of issues were fixed for the EdWeb distribution and new processes put in place to ensure that the distribution is updated and released quicker than has been the case previously.
  • Deployment planned for iteration 4 work and 40+ module updates for early July.
  • Started preparation work for Iteration 5, user stories written and estimation planned for start of iteration in early July

Issues

  • No issues to reportĀ 

Next StepsĀ 

  • Start iteration 5
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
124.0 days
Activity this month
26.0 days
Activity this year
85.0 days
Activity to date
85.0 days
Estimate to complete current year
28.0 days
Estimate to complete future years
2.0 days

Project Info

Project
EdWeb Collaboration Pilot and Feature Development
Code
UWP015
Programme
Z. ISG - University Website (UWP) (Closed)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Start Date
30-Sep-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Programme Priority
2
Overall Priority
Normal
Category
Discretionary

Documentation