Report for May 2018
- Report Date
- May 2018
Achievements in Last Period
- Further work to develop Telephone and Student Email Data APIsĀ
Issues
Milestones have slipped due to issues outlined in:
A PICCL has been submitted to WIS w/c 4/06/18 with new milestones to accommodate remedial actions to resolve these.
Next StepsĀ
- API development and Go Live
- Project Closure
- Approved budget
- 180.0 days
- Activity this month
- 18.6 days
- Activity this year
- 175.3 days
- Activity to date
- 175.3 days
- Estimate to complete current year
- 8.3 days
- Estimate to complete future years
- 0.0 days