Report for May 2018

Report Date
May 2018

Achievements in Last Period

  • Further work to develop Telephone and Student Email Data APIsĀ 

Issues

Milestones have slipped due to issues outlined in:

A PICCL has been submitted to WIS w/c 4/06/18 with new milestones to accommodate remedial actions to resolve these.

Next StepsĀ 

  • API development and Go Live
  • Project Closure
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
180.0 days
Activity this month
18.6 days
Activity this year
175.3 days
Activity to date
175.3 days
Estimate to complete current year
8.3 days
Estimate to complete future years
0.0 days

Project Info

Project
Implementation of procured University search service
Code
UWP016
Programme
Z. ISG - University Website (UWP) (Closed)
Management Office
ISG PMO
Project Manager
Emma Mcnab
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
01-Jun-2017
Planning Date
06-Oct-2017
Delivery Date
13-Dec-2018
Close Date
25-Jan-2019
Programme Priority
3
Overall Priority
Normal
Category
Compliance