Report for June 2018
- Report Date
- June 2018
Achievements in Last Period
- Go live of changes including cookies banner / GDPR alignment
Issues
Milestones have slipped due to issues outlined in:
A PICCL was submitted and approved at WIS w/c 4/06/18 with new milestones to accommodate remedial actions to resolve these.
Next StepsĀ
- API development and Go Live
- Project Closure
- Approved budget
- 185.0 days
- Activity this month
- 7.5 days
- Activity this year
- 186.4 days
- Activity to date
- 186.4 days
- Estimate to complete current year
- 3.1 days
- Estimate to complete future years
- 5.0 days