- Report Date
- January 2019
Achievements in Last Period
- Completion of "Must Have" jiras
- Agreement on BAU jiras
- Draft Closure Report
Issues
- Budget resolution required at programme level. The additional 15 days funding required to complete this project has been escalated to Programme Level.
Next Steps
- Approved budget
- 185.0 days
- Activity this month
- 0.4 days
- Activity this year
- 12.5 days
- Activity to date
- 203.0 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days