Report for February 2019

Report Date
February 2019

Achievements in Last Period

  • Draft Closure Report

Issues

  • Due to availability of PM the closure report has been delayed. This has now been drafted and closure is expected in early March. 

Next Steps 

  • Closure
Project Status
RAG Status
Time
RED
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
AMBER: Due to availability of PM the closure report has been delayed. This has now been drafted and closure is expected in early March.
Change Status
Time
Significant
Cost
No Change
Scope
No Change
Overall
Moderate
Has formal escalation taken place?
Yes
Escalated to
These issues have been escalated to Project Sponsor, Programme Manager, and Portfolio Manager previously.
Activity
Approved budget
185.0 days
Activity this month
0.4 days
Activity this year
13.0 days
Activity to date
204.0 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days

Project Info

Project
Implementation of procured University search service
Code
UWP016
Programme
Z. ISG - University Website (UWP) (Closed)
Management Office
ISG PMO
Project Manager
Emma Mcnab
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
01-Jun-2017
Planning Date
06-Oct-2017
Delivery Date
13-Dec-2018
Close Date
25-Jan-2019
Programme Priority
3
Overall Priority
Normal
Category
Compliance