- Report Date
- September 2018
Achievements in Last Period
- Remaining milestones re-planned
- Work packages outlined. Further work is being held off until the follow-on project is clarified
Issues
- Slight delay due to BA being off ill
Next Steps
- Finalise workshop sign off
- Close project
- Approved budget
- 150.0 days
- Activity this month
- 7.0 days
- Activity this year
- 41.0 days
- Activity to date
- 154.0 days
- Estimate to complete current year
- 5.0 days
- Estimate to complete future years
- 0.0 days