Report for November 2018

Report Date
November 2018

Achievements in Last Period

  • No work completed this month

Issues

  • Closure milestone moved out due to PM availability.

Next Steps

  • Close project
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Time
Moderate
Cost
No Change
Scope
No Change
Overall
Moderate
Has formal escalation taken place?
No
Activity
Approved budget
150.0 days
Activity this month
0.0 days
Activity this year
44.0 days
Activity to date
156.0 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days

Project Info

Project
Drupal 8 Implementation Planning
Code
UWP017
Programme
Z. ISG - University Website (UWP) (Closed)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
08-Aug-2017
Planning Date
07-Sep-2017
Delivery Date
28-Sep-2018
Close Date
11-Jan-2019
Programme Priority
2
Overall Priority
Normal
Category
Compliance

Documentation