Report for January
- Report Date
- January 2013
Achievements in Last Period
- Development Team have reviewed and feed into strategy and considerations document
- Fed into annual planning for the potential procurement and implementation project
- Estimate for project reduced based on findings to date (now 62.5 days was 88.5 days)
Issues
- Some conflicts for UWP time with Drupal proof of concept project
- Some conflicts for Project Services time with timetabling project
- Change to focus of project based on recommendation (i.e. data source and Information Architect roles are more immediate pressure than new search engine)
Next Steps
- Business Analysis to be signed off
- Agree scope for the remainder of project with project sponsor
Milestones
Target date | Title |
---|---|
05-Oct-2012 | Planning Review - Complete |
08-Feb-2013 | Strategy recommendation and considerations |
29-Mar-2013 | Business Case Review |
26-Apr-2013 | Closure |
- Approved budget
- 62.5 days
- Activity this month
- 3.3 days
- Activity this year
- 22.9 days
- Activity to date
- 23.4 days
- Estimate to complete current year
- 39.0 days
- Estimate to complete future years
- 0.0 days