Report for February

Report Date
February 2013

Achievements in Last Period

  • Strategy and considerations document agreed and signed off
  • Commenced investigation into practical "how to" using Google

Issues

  • Procurement project has been postponed until 2014/15 changing focus for project

Next Steps

  • Complete practical investigation

Milestones

 

Target dateTitle
05-Oct-2012Planning Review - complete
08-Feb-2013Strategy recommendation and considerations - complete
29-Mar-2013Business Case Review - milestone removed from scope - descoped
08-Apr-2013Practical Investigation - New
26-Apr-2013Closure

 

Project Status
Activity
Approved budget
62.5 days
Activity this month
8.8 days
Activity this year
32.3 days
Activity to date
32.3 days
Estimate to complete current year
30.2 days
Estimate to complete future years
0.0 days

Project Info

Project
Alternative Search Engine Investigation
Code
UWS005
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Craig Middlemass
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
23-Jul-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
08-May-2013