Report for February
- Report Date
- February 2013
Achievements in Last Period
- Strategy and considerations document agreed and signed off
- Commenced investigation into practical "how to" using Google
Issues
- Procurement project has been postponed until 2014/15 changing focus for project
Next Steps
- Complete practical investigation
Milestones
Target date | Title |
---|---|
05-Oct-2012 | Planning Review - complete |
08-Feb-2013 | Strategy recommendation and considerations - complete |
29-Mar-2013 | Business Case Review - milestone removed from scope - descoped |
08-Apr-2013 | Practical Investigation - New |
26-Apr-2013 | Closure |
- Approved budget
- 62.5 days
- Activity this month
- 8.8 days
- Activity this year
- 32.3 days
- Activity to date
- 32.3 days
- Estimate to complete current year
- 30.2 days
- Estimate to complete future years
- 0.0 days