Report for March

Report Date
March 2013

Achievements in Last Period

  • Practical investigation have been completed

Issues

  • None

Next Steps

  • Move to closing the project

Milestones

 

05-Oct-2012Planning Review - complete
08-Feb-2013Strategy recommendation and considerations - complete
08-Apr-2013Practical Investigation - complete (awaiting sign off)
26-Apr-2013Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
62.5 days
Activity this month
0.4 days
Activity this year
32.2 days
Activity to date
32.7 days
Estimate to complete current year
29.9 days
Estimate to complete future years
0.0 days

Project Info

Project
Alternative Search Engine Investigation
Code
UWS005
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Craig Middlemass
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
23-Jul-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
08-May-2013