Report for April
- Report Date
- April 2013
Achievements in Last Period
- Closure report written and sent out for approval
- Approval for closure agreed by email
Issues
- None
Next Steps
- Release days not spent back to programme
Milestones
05-Oct-2012 | Planning Review - complete |
08-Feb-2013 | Strategy recommendation and considerations - complete |
08-Apr-2013 | Practical Investigation - complete |
26-Apr-2013 | Closure - complete |
- Approved budget
- 62.5 days
- Activity this month
- 1.1 days
- Activity this year
- 33.3 days
- Activity to date
- 33.8 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days