Report for January 2021
- Report Date
- January 2021
Overview
There has been limited activity on the project since the cyber security assessment in July, as the IoT team have primarily focused on the study spaces SeatEd project.
We are still in planning mode, although some prototyping, design and testing work is being carried out in parallel. Technical architecture discussions with the EIDF team will inform our planning decisions. Once these are complete we can complete the brief and plan.
RAG status.
Although there has been a delay, given the significant impact from Covid-19 on DDI the UoE, and the CRD schools that will be the first users of the new version of the service, any delay to this project will be minor and not a cause for concern in itself.
Next steps:
Technical architecture discussions with the EIDF team.
Complete the project brief, technical designs, and plan.
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days