Report for November 2019

Report Date
November 2019
Status

In planning phase, which is expected to be complete by end of January.

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
IoT Research & Innovation Service Phase 2
Code
WCD001
Programme
EIDF IoT Programme (EID)
Management Office
ISG PMO
Project Manager
Steve Taylor
Project Sponsor
Simon Chapple
Current Stage
Close
Status
Withdrawn
Project Classification
Transform
Start Date
11-Sep-2019
Planning Date
30-Jul-2021
Delivery Date
17-Dec-2021
Close Date
31-Jan-2022
Overall Priority
Highest
Category
Discretionary

Documentation