Project Brief

Link to Project Brief and End of Planning  Sign Off

 

Version Control

Date

Change agreed

Version

Change

Made by

5/4

EdGEL Steering Group

1.1

O2D1 Insights report – moved to O1D1 as an appendix

SW

O1D3 Website review – Billy cant pick up to nearer end June – dates changed from 22/5-2/6 to 19-30Jun

O1D4 Style guide dates agreed as 6 Mar – 31 May (from 28 Apr)

 

O2D2 adoption strategy backlog document - moved out to end May so Karl can concentrate on other tasks

O3D2- Gap Analysis – Mairi’s time not required – removed from this task

 

Date changes have affected milestones – changes are

Recommendations to continue EdGEL was 28-Apr-17 now 30-Jun-17

Framework for delivering EdGEL was 23-Jun-17 now 30-Jun-17

 

12/5

Project Sponsor

1.1

EdGEL Style Guide V1.0 (O1 D4) - It is now a 'Review of the existing style guide'  - See piccl 5

SW

17/5

Project Sponsor

1.1

O3D1 Dropped ‘Initial’ from deliverable title  and Benefit– see piccl 6 17/5

SW

 

version 1.0 (17 Mar 17)

 

 

AttachmentSize
File dti007-project_brief-v1.0.docx33.04 KB

Project Info

Project
EdGEL as a Service
Code
DTI007
Programme
Digital Transformation - User Experience
Management Office
ISG PMO
Project Manager
Sue Woodger
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Start Date
20-Jan-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
28-Jul-2017
Overall Priority
Higher
Category
Discretionary