Report for August 2023

Report Date
August 2023

 

Report by Susan Ridder-Patrick (MVMLAT Programme Manager) for Philippa Burrell (MVMLAT Programme Owner) and Anne-Marie Coriat (MVM Portfolio Owner)

Distribution:

  • Vet and Medical School sub-group IT meeting
  • College Administration Team (CAT) meeting
  • College Undergraduate Learning and Teaching (CULT) committee
  • Post Graduate Learning and Teaching (PGLTC) committee
  • Excerpts taken into CSG report

Section One: Programme Commentary, RAG and Resources Update

Commentary

Programme status: The overall status of the MVMLAT programme for August 2023  is GREEN with two projects closing and three largely on track to deliver to plan.

There are five open programme risks in August:

Project highlights

  • MVM148: CLOSED - Project delivered and closed
  • MVM153: CLOSED - Project delivered and closed
  • MVM154: AMBER - Most of the work has now either completed or been rescheduled for completion. There are still outstanding supply only items that we are waiting for and these will need to be funded out of the 23/24 upgrade project budget.
  • MVM155: GREEN - Phases 3 and 3 completed development, UAT and deployed
  • MVM157: GREEN - Simulation electronic patient information system has been used three times; phase 2 planning to proceed

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

Forward Look - August 2023

Section Two: Projects Not Started 

Project Programme Manager's Commentary
MVM158 Student Placements project To be started as soon as resourcing available
Enhancements to EMS Proposed scope of work being defined
COMMAND User Interface Scheduled in 22/23

Section Three: Projects in Progress

MVM Learning and Teaching Projects Update

MVM148 Upgrading of teaching spaces 2021/22 RAG Status: CLOSED

Report by Alan Gilchrist

Achievements this period

  • EDSCCU rooms at Easter Bush have been completed and clinical staff have been asked to test the system and provide feedback.  Any adjustments to the configuration will be picked up either as business as usual or through the 23/24 teaching spaces upgrade project.
  • Request for updates on the remaining estates work for Vet School rooms has been sent.  Given the staff changeover and lack of information held on the estates side, work requests may need to be sent in again.  This will be dealt with as business as usual moving forwards, since the rooms are at least currently usable.
  • Closure report can be found at Closure Report

MVM153 Upgrading of student computer labs, teaching and meeting room PCs 2022/23 RAG Status: CLOSED

Report by Alan Gilchrist

Achievements this period

  • All new computers were installed in preparation for later year students returning on 7th August.
  • Closure report can be fount at Closure Report

MVM154 Upgrading of teaching spaces 2022/23 RAG Status: AMBER

Report by Alan Gilchrist

Achievements this period

  • AV contractor has replaced the temporary equipment they installed in the MSc area of the Anatomy lab.
  • AV contractor has been booked in to carry out the initial work in Dermatology clinic on 14th September.
  • Replacement desk monitors have been installed in the Anatomy lab to work with the surgical camera that was installed in July.  Old monitors couldn't support the low vertical refresh rate of the camera.
  • More of the supply only equipment has been delivered, however there are still outstanding items.
  • Two of the three Mackenzie Medical Practice rooms have been fully updated.  The third room has had all of the equipment updated, but there were issues getting the new AV desk into the room, so the AV contractor will return to complete this in September.  

Issues

  • NHS funding for Lauriston learning hub is apparently still available, following all of the delays with the building warrant being approved, however it is extremely unlikely that the necessary fabric and infrastructure work (organised by the NHS) will be completed before students return and no AV contractor has yet been appointed to the project.

Next Steps

  • Request network cable/ports for Dermatology clinic direct from data contractor and then update the associated netjob.
  • Receive remaining supply only AV equipment 

MVM155 BMS Honours Portal RAG Status: GREEN

Report by Chantal Reilly

Achievements in last period

  • Phase 2 developments
  • Phase 2 UAT
  • Phase 2 deployment 
  • Phase 3 developments
  • Phase 3 UAT
  • Phase 3 deployment

Issues ​

  • None to report

Next Steps ​

  • Earlier phase fixes
  • Phase 4 developments
  • Phase 4 UAT and accessibility testing
  • Phase 4 deployment

MVM157 Medical Simulation - Electronic Systems RAG Status: GREEN

Report by Alan Gilchrist

Achievements this period

  • Simulation electronic patient information system has so far been used on three occasions, twice for year 6 simulation and once for year 5 simulation.
  • Feedback survey for the year 5 simulation teaching has had it's first responses provided.

Issues

  • None

Next Steps

  • Nursing studies staff to generate more 'patients' for the system, so that they can be entered into the system.
  • Evaluate usage after the first 3 weeks of use to see if any adjustments need to be made to the system.
  • Start to plan the phase 2 objectives.

Projects outwith the MVM Portfolio Update

Report by Alan Gilchrist and Karen Howie (LTW):

OCP004 CPD Platform - Requirements, Market Analysis and Business Case - RAG Status: CLOSED

  • The  "Short Courses Platform - Requirements, Market Analysis and Business Case" project is now closed and has been superceeded by "SCP001 – Short Course platform procurement". A post project review will be completed

Please note that SCP001 is a secure project and will only be visible to those working on it.

VLE002 Learn Ultra: Technical - RAG Status: GREEN

Last month

  • VLE002:  Work on our list of Phase 2 developments for the 23/24 academic year is compete as per the plan.  
  • VLE002:  All integration work is complete to the extent the team can.  QMP is awaiting the migration of QMP project to finish and Linkedin Learning is compete and awaiting the service team for that product to publish the guidance.  

Issues.

  • No new issues.

Next steps.

  • VLE002:  Close the year 2 Technical workstream.
  • VEE002:  Highlight any scope required to be planned into year 3.  

VLE003 Learn Ultra: Learn Foundations - RAG Status: GREEN

Achievements

  • Continued migration of complex courses.
  • Continuation of the implementation work for the move to Learn Ultra (Focus on accessibility);
  • Completion of the new work package for out of scope uses of Learn - change to the project scope to include this piece of work;
  • Completion of both the Technical Implementation Group and Project Board (both scheduled for August 2023);
  • Continued planning to begin for the Evaluation phase of the Learn Ultra project.

Issues

  • Industrial action is currently underway and may have an impact upon aspects of the project - This is a risk that is actively being mitigated against as the UCU have just announced that their mandate has been renewed which confirms further potential strike action across the next academic year.

Next Steps

  • Finish the migration of complex courses by the end of September.
  • Finish the implementation work for the move to Learn Ultra (Focus on accessibility);
  • Begin the analysis of the Learn Foundations internship data obtained from June to September in preparation for School reports to be produced;
  • Initiation of the Evaluation phase of the programme;
  • Complete recruitment for an evaluation officer.

VLE004 Learn Ultra: Training and Support - RAG Status: GREEN

Achievements

  • We delivered 32 ’10 Things to get started in Learn Ultra’ training sessions in August to support colleagues in the move to Learn Ultra, meaning 186 sessions in total have been delivered so far, reaching 1131 colleagues. An additional 74 task-focussed training sessions have been delivered so far to 411 colleagues, thereby providing enhanced support for course build in preparation for the start of term.  
  • Launched a self-led online training resource called ‘Getting Started with Learn Ultra' that covers all the content taught in the live ‘10 Things to get Started in Learn Ultra’ sessions.
  • Provided Schools SMT with weekly training data for an overview of engagement with training from within the Schools.
  • Scheduled new ’10 Things’ training sessions ahead of semester 2.

Issues

  • Industrial action is currently underway and may have an impact upon aspects of the project. This is a risk that is actively being mitigated against as the UCU have just announced that their mandate has been renewed which confirms further potential strike action across the next academic year.

Next Steps

  • Finalise the schedule ahead of semester 2 by adding the drop-in sessions until the end of January.
  • Further schedule task-focussed sessions ahead of and after semester 2 as part of the regular Learn training programme.
  • Deliver 50 Ultra training and drop-in sessions across campuses in September.
  • Continue School SMT training data reporting.

SAC095 Student Support Enhancements - RAG Status: AMBER

Achievements in Last Period

  • Cohort Lead student allocation - search and display results screens LIVE (R1.0 and R1.0.6)
  • Cohort Lead student allocation - allocate students (and bulk allocate) LIVE (R1.0 and R1.0.6) 
  • Cohort Lead student allocation - display of allocation ("My Students" and MyEd view) in Test
  • Majority of PT reference changes deployed to Live (PATH - Live; ESC  - LIVE; SITS/EUCLID - Some Live; Student Hub - In test; Self-service - In test) 
  • MScR analysis completed; Technical input still required to allow user story documentation and develop
  • R1.1 scheduled for 11/9/23

Issues 

  • Model leadership elements of overall student support model still in development, so analysis work pushed back. Allows focus on Cohort Leadership roles in meantime

Risks:

  • Risk remains that effort required may be underestimated as significant areas need specified (especially model leadership roles)
  • Resource risk still live with conflicting demands on developer/BA time for Marking and Assessment Boycott and ESC

Next Steps​

  • Remaining PT reference changes
  • MScR development analysis
  • Model Leadership (and Senior Tutor) analysis
  • R1.1 (List my cohort students) packaging, agreement with production management, release (11/9/23) and post-live support
  • R1.3 - UX and Enhancements - Prioritisation of development TBC

Section Four: Closed or Withdrawn Projects

Only those projects closed from August 2021 onwards are included in this table. A full history of completed projects is available on the programme's website.

Project Info Project Manager's Commentary
MVM139 Curriculum Mapping Tool (COMMAND) This project started in January 2020 and closed on 13 August 2021. The Closure Report is available to view.
MVM125 Connectivity Off-campus This project started in February 2019 and closed on 19 October 2021. The Closure Report is available to view.
MVM144 Upgrading of student computer labs, teaching and meeting room PCs 2020/21 This project started in October 2020 and closed on 5 November 2021. The Closure report is available to view.
MVM143 Upgrading of Teaching Spaces 2020/21 This project started in October 2020 and closed on 31 January 2022. The Closure Report is available to view.
MVM141 Replacement for PathCAL/EROS and Labyrinth This project started in October 2020 and closed on 23 June 2022. The Closure Report is available to view.
MVM149 Year 4 Outpatient Booking System This project started in May 2022 and closed on 2 August 2022. The Closure Report is available to view.
MVM150 BMS Honours Project portal enhancements This project started in May 2022 and closed on 2 August 2022. The Closure Report is available to view
MVM147 Upgrading of student computer labs, teaching and meeting room PCs 2021/22 This project started in November 2021 and closed on 6 September 2022. The Closure Report is available to view.
MVM151 Rotations Feedback This project started in May 2022 and closed on 29 September 2022. The Closure Report is available to view.
MVM152 BMS HHW & HHW2 upgrades This project started in September 2022 and closed on 31 October 2022. The Closure Report is available to view.
MVM145 Accessibilty for MVMLAT applications This project started in Decemeber 2020 and closed on 7 March 2023. The Closure Report is available to view.
MVM156 Medical Schools Council - Online Exams BYOD This project started in January 2023 and closed on 30 June 2023. The Closure Report is available to view.
MVM140 CMVM eAssessment This project started in July 2020 and closed on 20 July 2023. The Closure Report is available to view.

Section Five: Programme Meeting Minutes

Notes and actions for all programme meetings are available on the MVMLAT website. Only the most recent five meetings' direct links are included in this table:

Date Notes and actions
17 August 2023 Programme Review Monthly Meeting - July 2023
20 July 2023 Programme Review Monthly Meeting - June 2023
15 June 2023 Programme Review Monthly Meeting - May 2023
12 May 2023 Programme Review Monthly Meeting - April 2023
21 April 2023 Programme Review Monthly Meeting - March 2023

Section Six: MVM Portfolio Projects Update 

The MVM Portfolio contains three programmes: CMVM Learning and Teaching - MVMLAT (this programme); CMVM Business Administration - MVMBUS and CMVM Research - MVMRES. Information on current work in MVMBUS and MVMRES are available on the following websites:

Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?
No

Documentation