Skip to main content
Toggle section links
Views
Projects
Programmes
Portfolios
Requests
New Project
New Programme
New Portfolio
Help
Schools & departments
MyEd
Search:
Search
KB-New Waddington Building Project
KB-New Waddington Building Project
Home
Projects
KB-New Waddington Building Project
Status
Monthly Report
Monthly Report
Report Date
December 2017
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days
This article was published on
Jan 16, 2018
Project Info
Project
KB-New Waddington Building Project
Code
AV2696B
Programme
ISG Learning and Teaching Spaces: Estates (AV)
Management Office
ISG PMO
Project Manager
John Power
Project Sponsor
Steven Poliri
Current Stage
Close
Status
Closed
Start Date
06-Dec-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Jul-2018
Overall Priority
Normal
Category
Compliance
More project information
Documentation
Not available.