Current project status

Report Date RAG Budget Effort Completed Effort to complete
August 2024 GREEN 0.0 days 0.0 days 0.0

Project Info

Project
Engineering Sanderson CR2 & CR3
Code
AV3064
Programme
ISG Learning and Teaching Spaces: CSE (AV)
Management Office
ISG PMO
Project Manager
Richard Leslie
Project Sponsor
Fraser Millar
Current Stage
Close
Status
Closed
Start Date
01-Jun-2024
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Sep-2024
Overall Priority
Normal

Documentation