Report for January 2017
- Report Date
- January 2017
Achievements in Last Period
- Vendors have been on site to install software upgrades and test these
- Business partners to undertake user testing of upgrades on new servers
- Discussions with business partners and Production Management about deployment
Issues and Risks
- Some delays to getting exact configuration on new servers exactly as required
- This has pushed back the completion of UAT and the window for deployment
- Milestones to be revised
Next Steps
- Business partners to complete UAT
- Preparations for deployment to be drawn together
- Switchover to new infrastructure
Project status is AMBER because of need to revise outstanding milestones.
Milestones
28-Feb-2017 | Acceptance sign-off (tbc) |
05-May -2017 | Deployment sign-off (tbc) |
19-May-2017 | Project closure (tbc) |
- Approved budget
- 23.0 days
- Activity this month
- 9.4 days
- Activity this year
- 20.8 days
- Activity to date
- 20.8 days
- Estimate to complete current year
- 2.5 days
- Estimate to complete future years
- 0.0 days