Report for April 2017
- Report Date
- April 2017
Achievements in the last period
- Project initiated and scoped.
- Brief drafted and agreed
- UX Workshops planned
Issues
-
None
Next steps
- Identify, book & involve development resources
- Delivery of UX workshops by Web UX team
Milestones
| Target Date |
Previous Date | Title | Stage | Complete | |
|---|---|---|---|---|---|
| 21-Apr-2017 | No date available | Brief sign-off | Plan | Yes | |
| 21-Apr-2017 | No date available | Planning sign-off | Plan | Yes | |
| 25-May-2017 | No date available | Discovery end: UX Requirements and back-end analysis defined & signed off | Analyse | No | |
| 25-May-2017 | No date available | Back-end design sign-off | Analyse | No | |
| 24-Jul-2017 | No date available | Development Build Sign-off | Build | No | |
| 25-Jul-2017 | No date available | Install in Test | Integrate | No | |
| 27-Jul-2017 | No date available | Integration / system test sign-off | Integrate | No | |
| 04-Aug-2017 | No date available | User Acceptance sign-off | Accept | No | |
| 07-Aug-2017 | No date available | Deploy to live | Deliver | No | |
| 08-Aug-2017 | No date available | Deployment / handover to support sign-off | Deliver | No | |
| 22-Aug-2017 | No date available | Post-implementation support sign-off | Deliver | No | |
| 29-Aug-2017 | No date available | Project Closure | Close | No |
- Approved budget
- 154.0 days
- Activity this month
- 6.5 days
- Activity this year
- 6.5 days
- Activity to date
- 6.5 days
- Estimate to complete current year
- 109.4 days
- Estimate to complete future years
- 37.2 days