Report for April 2017

Report Date
April 2017

Achievements in the last period

  • Project initiated and scoped. 
  • Brief drafted and agreed
  • UX Workshops planned

Issues

  • None

Next steps

  • Identify, book & involve development resources
  • Delivery of UX workshops by Web UX team

Milestones

 

Target Datesort descending Previous Date Title Stage Complete  
21-Apr-2017  No date available  Brief sign-off Plan Yes

 view

21-Apr-2017  No date available  Planning sign-off Plan Yes

 view

25-May-2017  No date available  Discovery end: UX Requirements and back-end analysis defined & signed off Analyse No

 view

25-May-2017  No date available Back-end design sign-off Analyse No

 view

24-Jul-2017  No date available Development Build Sign-off Build No

 view

25-Jul-2017  No date available Install in Test Integrate No

 view

27-Jul-2017  No date available Integration / system test sign-off Integrate No

 view

04-Aug-2017  No date available User Acceptance sign-off Accept No

 view

07-Aug-2017  No date available Deploy to live Deliver No

 view

08-Aug-2017  No date available Deployment / handover to support sign-off Deliver No

 view

22-Aug-2017  No date available Post-implementation support sign-off Deliver No

 view

29-Aug-2017  No date available Project Closure Close No

 view

   
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
154.0 days
Activity this month
6.5 days
Activity this year
6.5 days
Activity to date
6.5 days
Estimate to complete current year
109.4 days
Estimate to complete future years
37.2 days

Project Info

Project
ESPA Website
Code
CSG012
Programme
CSG Portfolio Projects (OTHCSG)
Management Office
ISG PMO
Project Manager
Nikki Stuart
Project Sponsor
Eliane Reid
Current Stage
Close
Status
Closed
Start Date
11-Apr-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Jul-2018
Overall Priority
Normal
Category
Discretionary